Question: 1/50
During an Aria Automation design workshop, stakeholders present multiple requirements that conflict (e.g., "self-service with no approvals" and "all production changes require CAB approval"). What is the BEST next step in a formal design methodology?
Document the conflict as a risk and proceed with the original timeline
Facilitate a requirements validation session to prioritize and resolve conflicts, then baseline agreed requirements
Select the most technically feasible requirement set and design around it
Create two separate designs and let the implementation team choose later