Question: 1/50
A new stakeholder with high influence joins the project after planning is complete and requests additional reporting. What should the project manager do FIRST?
Update the stakeholder register and assess the new stakeholder’s engagement needs
Add the requested reports to the status report immediately to maintain satisfaction
Ask the sponsor to deny the request to prevent scope creep
Rebaseline the project schedule to include time for additional reporting