Question: 1/50
During Sprint Planning, the Product Owner asks the Developers to add several items that are not in the Product Backlog because an executive mentioned them in the hallway. What is the best Scrum-aligned response?
Add the items to the Sprint Backlog immediately to show responsiveness
Ask the Product Owner to add the items to the Product Backlog and order them; then consider them for the Sprint if they are ready and valuable
Have the Scrum Master add the items directly to the Sprint Backlog to keep planning moving
Delay Sprint Planning until the executive can attend and clarify priorities