Question: 1/50
During a Sprint, a stakeholder asks the Developers to add a “small, urgent” feature immediately. The work was not in the Sprint Backlog. What is the best Scrum-based response?
The Developers add it right away because responding to change is more important than following a plan.
The Product Owner discusses the request and, if valuable, works with the Developers to negotiate changes to the Sprint Backlog without endangering the Sprint Goal.
The Scrum Master approves the request and updates the Sprint Backlog to reflect it.
The request must wait until the next Sprint because the Sprint Backlog cannot change once the Sprint starts.