200-301 Question 34

Single answer

A network engineer is deploying IP cameras across a new office building and plans to use Power over Ethernet (PoE) to power the devices. The switch being used supports IEEE 802.3at (PoE+). However, some IP cameras require more power than the switch can supply. What action can the engineer take to ensure the cameras receive adequate power?

  1. A

    Deploy a midspan injector between the switch and the IP cameras

  2. B

    Upgrade the switch to one that supports IEEE 802.3bt

  3. C

    Use a PoE splitter to reduce the power demand of each IP camera

  4. D

    Disable PoE on unused switch ports to allocate more power to active ports

Show answer and explanation

Correct answer: B

Explanation

The IEEE 802.3at (PoE+) standard provides up to 25.5 watts of power per port. If devices require more power, upgrading to a switch that supports IEEE 802.3bt (which provides up to 60-100 watts per port) is necessary. Other options either do not address the specific problem or cannot increase the per-port power beyond the standard's limits.

  • A. Incorrect.

    Deploying a midspan injector can add PoE capabilities to a non-PoE switch, but it will not resolve the issue if the power demands of the IP cameras exceed the capabilities of the switch or the IEEE 802.3at standard.

  • B. Correct.

    Upgrading to a switch that supports IEEE 802.3bt increases the available power per port and is the correct solution when devices require more power than IEEE 802.3at can provide.

  • C. Incorrect.

    A PoE splitter is used to separate power and data for non-PoE devices. It does not reduce the power demand of PoE devices, so this option is incorrect.

  • D. Incorrect.

    Disabling PoE on unused ports does not affect the per-port power allocation; it only frees up the overall PoE budget of the switch. This does not help when a device requires more power per port than the current standard supports.