1Z0-1123-25 exam dumps

1Z0-1123-25 practice question 83 of 150

Oracle Cloud Infrastructure 2025 Migration Architect Professional. Professional level, Oracle. Free question with the correct answer and a full explanation.

1Z0-1123-25 Question 83

Single answer

You need to migrate a three-tier application running on a VMware-based on-premises data center to an Oracle Cloud VMware Solution environment. The application� database is critical and cannot tolerate more than a brief disruption. You have deployed the Hybrid Cloud Extension (HCX) component and established network connectivity. Which migration strategy will best minimize downtime for the final cutover in this scenario?

  1. A

    Perform a cold migration of the virtual machines using HCX during business hours.

  2. B

    Use HCX Replication-Assisted vMotion to replicate the workloads and schedule a cutover during a low-traffic window.

  3. C

    Rely on native VMware vMotion alone to migrate all workloads in real time without replication.

  4. D

    Export the VMs as OVAs from on-premises and import them into Oracle Cloud VMware Solution.

Show answer and explanation

Correct answer: B

Explanation

In production environments with minimal downtime requirements, using Hybrid Cloud Extension (VMware HCX) with Replication-Assisted vMotion (RAV) is the recommended strategy. It replicates the workloads to Oracle Cloud VMware Solution over time, then performs a quick cutover when ready. This minimizes user impact and downtime, aligning with best practices found in Oracle Cloud VMware Solution documentation and VMware HCX guidelines.

  • A. Incorrect.

    Incorrect. Cold migration in the middle of business hours would cause a complete outage of the application for the duration of the transfer. This does not meet the requirement of minimizing downtime.

  • B. Correct.

    Correct. HCX Replication-Assisted vMotion (RAV) creates a replica of the VM in the cloud and then synchronizes changes before performing a final switchover. This approach significantly reduces downtime by deferring the cutover to a maintenance window or off-peak period.

  • C. Incorrect.

    Incorrect. While VMware vMotion alone can work for some migrations, it typically requires a dedicated low-latency network, and large-scale data transfers without replication can take a long time. This approach may not guarantee minimal downtime for a critical workload, especially if network bandwidth or latency is limited.

  • D. Incorrect.

    Incorrect. Exporting and importing OVAs is a manual process that can introduce both extended downtime and configuration discrepancies. This approach is neither seamless nor optimized for large-scale VMware migrations with strict uptime requirements.

Timed practice exam

Take a 1Z0-1123-25 practice test under exam conditions

50 questions in 90 minutes, drawn from this bank, with a score report and a per-question review when you finish.

Start timed exam