2V0-32.24 Question 74

Select 3

During the installation and configuration of vRealize Operations Manager, you need to ensure that the product is integrated with vCenter Server to enable monitoring and alerting for your virtual environment. Which steps are required to successfully integrate vRealize Operations Manager with vCenter Server?

  1. A

    Add the vCenter Server as a new adapter instance in vRealize Operations Manager.

  2. B

    Install the vRealize Operations Manager appliance and configure a cluster node.

  3. C

    Provide vCenter Server credentials with appropriate permissions in the integration settings.

  4. D

    Enable the vSphere Web Client plugin for vRealize Operations Manager.

  5. E

    Deploy a dedicated vRealize Operations Manager agent on each ESXi host.

Show answer and explanation

Correct answers: A, C, D

Explanation

To integrate vRealize Operations Manager with vCenter Server, you must add the vCenter Server as a new adapter instance and provide valid credentials to enable data collection. Additionally, enabling the vSphere Web Client plugin ensures seamless access to monitoring and alerting features. Steps like deploying a dedicated agent on each ESXi host are unnecessary for this integration.

  • A. Correct.

    Correct: Adding the vCenter Server as a new adapter instance in vRealize Operations Manager is a required step for integration. This allows data collection from the vCenter Server.

  • B. Incorrect.

    Incorrect: Installing the vRealize Operations Manager appliance and configuring a cluster node is part of the product setup, but it is not specific to integrating with vCenter Server.

  • C. Correct.

    Correct: Providing vCenter Server credentials with appropriate permissions ensures that vRealize Operations Manager can authenticate and communicate with vCenter Server.

  • D. Correct.

    Correct: Enabling the vSphere Web Client plugin for vRealize Operations Manager allows administrators to access monitoring and insights directly from the vSphere Web Client, completing the integration.

  • E. Incorrect.

    Incorrect: Deploying a dedicated vRealize Operations Manager agent on each ESXi host is not required for integration with vCenter Server. Data collection is handled through the vCenter Server adapter.