2V0-41.24 Question 29
Select 3An organization is deploying VMware NSX in their environment. They have completed installing the NSX Manager and need to proceed with the next steps to prepare their infrastructure for NSX. Which of the following are part of the deployment workflow for the NSX infrastructure?
- A
Register the NSX Manager with vCenter Server
- B
Deploy NSX Edge appliances before installing NSX-T Data Center components
- C
Configure transport zones and transport nodes
- D
Establish the management plane to control plane communication
- E
Install NSX Agents on ESXi hosts manually
Show answer and explanation
Correct answers: A, C, D
Explanation
The workflow for deploying the NSX infrastructure includes registering the NSX Manager with vCenter Server, configuring transport zones and transport nodes, and ensuring proper communication between the management plane and the control plane. These steps are critical to setting up the NSX environment before moving on to more advanced configurations like Edge deployment or logical networking setup.
- A. Correct.
Registering the NSX Manager with vCenter Server is a necessary step to integrate NSX Manager with the virtual infrastructure, enabling it to manage network virtualization.
- B. Incorrect.
Deploying NSX Edge appliances is not required at this stage of the workflow. This step typically occurs after configuring transport zones and nodes.
- C. Correct.
Configuring transport zones and transport nodes is a critical step in preparing the infrastructure for NSX. It defines the boundaries for logical switching and routing.
- D. Correct.
Establishing the management plane to control plane communication ensures that NSX Manager can communicate with NSX controllers and transport nodes, which is essential for the NSX deployment.
- E. Incorrect.
Installing NSX Agents manually on ESXi hosts is not required as the NSX Manager automates the process of installing NSX VIBs (vSphere Installation Bundles) on ESXi hosts.